G702/G703 Excel Template Alternative

Enter your schedule of values, percent complete and retainage rate. Completed work, retainage held and current payment due are calculated for you.

Line item (Schedule of Values)Scheduled value% completeCompleted to date
$
%
$0.00
$

Want next month's draw to auto-fill your previous payments?

Sign up free, upgrade to Pro whenever you're ready.

Sign up free

The problem with Excel pay app templates

An Excel G702/G703 works until someone changes a row. Then percentages stop adding up, retainage is off by a few hundred dollars, and last month’s numbers do not carry forward cleanly. A calculator that enforces the math removes that risk.

What the math has to do

  • Work completed to date = Scheduled value × percent complete, plus stored materials.
  • Retainage = Work completed × retainage rate.
  • Total earned less retainage = Amount earned.
  • Current payment due = Total earned less retainage, less previous payments.

Where errors usually hide

  • Previous payments not matching what was actually paid.
  • Percent complete entered as more than 100% on a line.
  • Retainage calculated on the wrong base.
  • Change orders added to the contract sum but not the schedule of values.

Run your numbers through the calculator to cross-check your Excel, or use it as the source and copy the totals onto your AIA form. This is a calculation tool; the official AIA forms are a copyrighted product of the AIA.

Carry draws forward

Each month’s application starts from last month’s completed work. DrawTrack Pro saves each draw per project and carries previous payments forward automatically.

Frequently asked questions

Is a G702/G703 Excel template free?

Excel versions are widely available, but the official AIA documents are sold by the AIA. This free calculator handles the math and is not a replacement for the official forms.

What is the difference between G702 and G703?

The G702 is the application and certificate for payment summary. The G703 is the continuation sheet with the line-item schedule of values.

How is current payment due calculated?

Take total completed and stored, subtract retainage, then subtract the amount of previous certificates for payment.

Is the calculator free?

Yes, free with no account. DrawTrack Pro is $15/month and saves every draw per project.