Retainage Release Calculator

Enter your contract and percent complete to see the retainage held on the job, the amount you can expect when it is released.

Line item (Schedule of Values)Scheduled value% completeCompleted to date
$
%
$0.00
$

Want next month's draw to auto-fill your previous payments?

Sign up free, upgrade to Pro whenever you're ready.

Sign up free

What retainage release means

Retainage is the portion of each progress payment held back until a milestone, often substantial completion or final acceptance. When that milestone is reached, the held amount is released, usually through a final application for payment.

What retainage you will have at the end

On a $250,000 contract with a 10% retainage rate and the full contract completed, retainage held is $25,000. That is real money you earned and have not been paid, so release timing matters to cash flow.

Getting retainage released faster

  • Know exactly which milestone triggers release in your contract.
  • Close out punch list items quickly.
  • Submit closeout documents, warranties, lien waivers and as-builts as required.
  • Send the final application promptly and follow up on the owner’s review.

Laws and rules differ

Retainage rules, including rate limits and the time owners have to release it, vary by state and contract type. Check your contract and your state’s requirements, and consult an attorney for a dispute.

Frequently asked questions

When is retainage released?

The contract sets the trigger, commonly substantial completion or final completion. Some contracts release part at an earlier milestone.

Can an owner hold retainage indefinitely?

Many states set limits or require timely release of retainage. Rules vary, so check your contract and local law.

How do I calculate retainage held?

Multiply the work completed to date by the retainage rate. At 10% on $250,000 of completed work, that is $25,000.

Is the calculator free?